- Shaanxi Pucheng Power Plant Third Stage Project 2X600MW Pneumatic Fly-ash Project (in 2008)
Conveying distance: equivalent length 550m; Design output: 140.0t/h per furnace Control: PLC and upper computer
- Liaoning Fuxin Power Plant 2X300MW Pneumatic Fly-ash Rebuilding Project
Equivalent length: 1000m; Actual output per furnace: 19.2t/h Control: PLC and upper computer